Herman and Lynn's Home construction progress - August 2007

August 23 2007

Roofing nearly completed, HVAC Ductwork being installed inside and electrical wiring started.
The Track Hoe is being used to build a stone retaining wall on the right side.




August 26 2007

The roofing, retaining wall and rough grading work are completed. Additional HVAC ductwork and electrical wiring have also been completed.
The bulldozer operator worked like an artist while shaping the grade to drain water properly around the house.




August 30 2007

This begins the installation of windows.




August 30 2007

The double french doors in the background will swing outward onto a deck.




August 30 2007

The short wall in the foreground will be the back of the counter where a sink will be located and will have an overhanging bar on top.